Accepted Convergence record

Hut 8 Beacon Point lease doubles beyond financed scope

The new 704 MW contract expands delivery commitments, but the closed financing and cash waterfall still map only to the first 352 MW.

Latest Convergence issue · July 23, 2026There is no open investigation right now.
Featured full report

Hut 8's public sequence now shows two different Beacon Point states. The May first-quarter filing tied the original lease to 352 MW, about $9.8 billion of 15-year base contract value, expected average annual NOI, and Q3 2027 initial delivery. The June financing record then scoped six data halls and 352 MW, followed by the completed $4.25 billion secured-note offering and a Phase 1 cash waterfall. On July 20, Hut 8 disclosed a second 15-year lease adding another 352 MW, doubling contracted Beacon Point capacity to 704 MW, with initial Phase 2 delivery in Q2 2028.

the contract state has moved ahead of the disclosed financed state. The closed record supports one financed and cash-modeled 352 MW phase plus one separately contracted 352 MW phase, not a 704 MW campus already shown as sharing the June debt scope or waterfall. That distinction matters because the June model is the company's disclosed conversion path from lease economics into debt service and levered cash flow, but it is attached to Phase 1 capacity. A professional reader should therefore underwrite Beacon Point in two layers: funded Phase 1 and contracted Phase 2 pending a new capital-stack or scope-expansion disclosure. The read breaks if another filing shows the June financing already covered both phases or was always intended for the full 704 MW campus.

Up next

Inside the current research file

These are accepted stories, ordered as a reading path. This research has not yet been published as a new Convergence issue.

Previous issues / accepted record

Accepted research briefs

Only a fully cleared issue enters this record. Hut 8 remains the sole accepted issue; the current file above is displayed separately so freshness never becomes fabricated certainty.

AcceptedJuly 23, 2026
Single source family · SEC EDGAR

Hut 8 Beacon Point lease doubles beyond financed scope

The new 704 MW contract expands delivery commitments, but the closed financing and cash waterfall still map only to the first 352 MW.