The Numbers Disagree · Construction materials · Middle East Africa

Cement prices in the UAE have outrun the forecast for building costs

Buyers of construction work carry more of the risk of rising prices when a quoted price for some materials may be guaranteed for only about a month, and one cement producer says its average selling price is higher than a year ago.

A cement plant at Dibba Al Hisn in the United Arab Emirates, its two kiln towers in front of the Hajar Mountains, with heaps of raw material in the foreground
A cement plant at Dibba Al Hisn in the United Arab Emirates, its two kiln towers in front of the Hajar Mountains, with heaps of raw material in the foregroundPhoto: Mike Che · CC BY-SA 3.0 · Wikimedia Commons

For some materials, including steel, a quoted price may now be held for only around 30 days, Construction Business News Middle East reported this week. Buildings take rather longer than that to finish.

That short promise sits beside two numbers that pull apart. Since January, average cement prices have risen by 16%, TradeArabia reported, faster than concrete and twice as fast as reinforcement steel. Yet Gulf Construction reported on March 1 that cost escalation in the UAE is forecast at around three per cent this year. Both figures can be right, because cement is one line in a budget. The likelier reading, however, is that the calm forecast hides a transfer: the risk of rising prices is passing from the firms that quote them to whoever pays for the building.

Cement has risen twice as fast as reinforcement steel since JanuaryRise in average UAE prices of three building materials since January, per cent, as reported by TradeArabiaCement has risen twice as fast as reinforcement steel since JanuaryRise in average UAE prices of three building materials since January, per cent, as reported by TradeArabiaCement16 %Concrete10 %Reinforcement steel8 %Diesel prices, not shown, remained volatile over the same period.

Swipe sideways to see the whole chart. The data is under it.

Source: TradeArabia, Oct. 1, 2026
Show the data
Figure data: Cement has risen twice as fast as reinforcement steel since January
ItemValue
Cement16%
Concrete10%
Reinforcement steel8%

Currie & Brown said in its latest UAE Construction Market Overview, as TradeArabia reported, that those quoting prices are less willing to hold them fixed for long periods. The result, it said, is shorter price guarantees, more conditions on tenders, the bids submitted for work, and greater use of fluctuation clauses. A fluctuation clause lets a contract price move with the cost of materials. Cement is not moving alone, either: TradeArabia's figures show concrete and reinforcement steel rising since January, while diesel prices have remained volatile.

Schedules are under strain as well as budgets. TradeArabia also reported that shortages in contractor capacity and specialist procurement are increasing the risk of delays. Construction Business News Middle East reported this week that requests for extra time to finish a job are becoming more common.

Where the extra money goes is easier to see from the other side of the sale. EMSTEEL, which sells both steel and cement, said in a second-quarter results release dated Aug. 27 that its cement division recorded revenue of AED 287 million and EBITDA of AED 75 million. EBITDA, earnings before interest, tax, depreciation and amortisation, is a rough measure of operating profit. Cement and clinker sales reached 1.1 million tonnes, the company said.

The growth rates behind those totals are the more telling part. Average selling prices for cement products, sales volumes and revenue each rose by a similar share from a year earlier, according to EMSTEEL's release, which credited continued strong market demand. Operating profit grew far faster than any of them.

Those rates do not multiply out. A division that sold that many more tonnes at prices that much higher would ordinarily report revenue growth well above either rate, not level with both. One possible reason sits in EMSTEEL's wording: the price figure covers cement products, while the volume figure covers cement and clinker, the half-finished material that is ground into cement. If so, the reported rise in prices may overstate what the average tonne earned.

Even on that cautious reading, the division kept more of each dirham it took in. Khaleej Times reported on Aug. 2 that EBITDA margin expanded to 26.1 per cent from 22.8 per cent in the same period last year. The paper credited strong demand and higher average cement selling prices. That margin matches the cement division's profit and revenue as EMSTEEL published them.

Alpha’s call · sealed Oct. 1

80%

chance by Dec. 15, Alpha’s estimate

Will EMSTEEL's cement division report an EBITDA margin of at least 22.8 per cent for the third quarter of 2026?

no market odds on this question · settled by EMSTEEL investor relations

Holds if EMSTEEL's cement division reports a third-quarter EBITDA margin at or above 26.1 per cent, with average selling prices still higher than a year earlier.

Breaks if the division's third-quarter EBITDA margin falls below 22.8 per cent, or it reports average selling prices no higher than a year earlier.

Falling below 22.8 per cent would take a drop of more than three points in one quarter while cement prices have risen 16 per cent since January.

Alpha’s record, scored in public →

The whole company gained too. Gulf News reported on July 31 that EMSTEEL's net profit rose 157% year on year to Dh262 million in the second quarter. The paper said higher steel and cement prices, cost controls and continued demand from the UAE construction market supported the result. That suggests the increases are more than list prices; they are reaching a producer's accounts.

A Calmer Account

A calmer account exists, and it has evidence. Stonehaven's GCC Construction Cost Index said at the start of June that cement remained anchored at AED 280 per tonne, with no movement that week. The same issue said the index had eased to 125.69, down 0.60% from the week before. That is one week in one tracker. Separately, Gulf Construction reported on March 1 that building activity in the UAE is expected to grow at a steadier pace this year, which could take some heat out of demand.

On that view, cement is one line among many, a weekly price can sit still, and short quotes reflect scarce capacity as much as dearer materials. The first quarter lends the view some support. Zawya, carrying a WAM report on May 13, said EMSTEEL's cement division recorded revenue of AED269 million and EBITDA of AED80 million in the first quarter. That works out to a margin of about 29.7%. Revenue rose between the two quarters; operating profit fell. Pricing power that was still building would probably have made the second quarter the richer one.

Materials are a large part of a building budget. Turner & Townsend said in its UAE market report for last year that materials amount to around 60 percent of the baseline cost of construction. That figure is last year's and covers all materials, not only the three TradeArabia tracked, so it does not show whether those rises break the forecast for the whole.

A forecast is an average, and a buyer on an unfixed price does not pay the average. A fluctuation clause passes each increase through as it arrives. A quote that may be held for only about a month has to be renewed at whatever the market then asks. Either way, the party that once promised a price now promises less, and the party paying for the building carries what is left.

Builders sit in the middle. Gulf Construction also reported on March 1 that labour shortages and higher material prices continue to add delivery risk. A builder that has promised its client a fixed price while buying materials on short quotes carries the gap itself; one with a fluctuation clause passes it on. Delay would compound either position, since a late project buys its materials later.

Producers hold the other end, and their results offer the cleanest test. Suppose EMSTEEL's cement division reports a third-quarter margin at or above its second-quarter level, with selling prices still above a year earlier. That would show the increases sticking, and the unfixed prices would be a real cost. A margin back below the level of the second quarter a year ago, or selling prices no higher than a year before, would favour the calmer account. So would a longer price hold in Currie & Brown's next overview.

Cement is dearer, prices for some materials may be held for only about a month and one producer's margin is wider than a year ago. The forecast for the whole market may yet prove right. It says little about the risk a buyer takes on once the price stops being fixed.

Alpha’s record

Resolved
9
Brier
0.240
Open
77
Full record

Sources

TradeArabiaConstruction Business News Middle East Sept. 30EMSTEEL Aug. 27Khaleej Times Aug. 2Gulf News July 31Zawya May 13Stonehaven GCC Construction Cost Index June 1Gulf Construction March 1Turner & Townsend UAE Market Intelligence 2025

25 statements, each tied to its sourceWhat each statement rests onHow ARCANE checks a story

Sources
S1TradeArabiaRetrieved Oct 1, 2026
S4Khaleej TimesRetrieved Oct 1, 2026
S5Gulf NewsRetrieved Oct 1, 2026
S8Gulf ConstructionRetrieved Oct 1, 2026
All 9 sources were retrieved from their exact links, so a later change to any of them would be detectable
What each statement rests on (25)
reportedS1

Since January, average cement prices have risen by 16%, concrete by 10% and reinforcement steel by 8%, while diesel prices have remained volatile.

reportedS2

For some materials, including steel, this means prices may now only be held for around 30 days.

reportedS1

They're less willing to hold fixed prices for long periods, leading to shorter price guarantees, more conditions on tenders and greater use of fluctuation clauses, said Currie & Brown in its latest UAE Construction Market Overview.

reportedS1

Shortages in contractor capacity and specialist procurement are increasing the risk of delays.

reportedS2

Extension-of-time claims are also becoming more common.

reportedS3

Cement division robust financial performance was supported by continued strong market demand, and a 30% YoY increase in average selling prices for cement products.

reportedS3

Cement and clinker sales volumes increased by 28% YoY, reaching 1.1 million tonnes, reflecting continued strong demand for cement products during the period.

reportedS3

EMSTEEL's Cement division recorded revenue of AED 287 million in the second quarter of 2026, representing a 29% YoY increase, with EBITDA of AED 75 million, up 47% YoY.

reportedS4

EBITDA margin expanded to 26.1 per cent from 22.8 per cent in the same period last year, supported by continued strong market demand and a 30 per cent increase in average cement selling prices.

reportedS5

EMSTEEL's net profit rose 157% year on year to Dh262 million in the second quarter of 2026, supported by higher steel and cement prices, cost controls and continued demand from the UAE construction market.

reportedS6

EMSTEEL's cement division recorded revenue of AED269 million in Q1 2026, representing a 31 percent YoY increase, with EBITDA of AED80 million, up 100 percent YoY.

reportedS7

Cement remains anchored at AED 280 per tonne and ready-mix concrete at AED 410 per cubic metre, with no movement this week.

reportedS7

The SCI eases to 125.69, down 0.60% WoW.

reportedS8

In the UAE, construction activity is expected to grow at a steadier pace in 2026, with cost escalation forecast at around three per cent.

reportedS8

Labour shortages and higher material prices continue to add delivery risk.

reportedS9

There has been a notable increase in construction material prices, with materials in the UAE now amounting to around 60 percent of construction baseline costs.

calculated

Cement's 16% rise since January is twice reinforcement steel's 8% rise (16 / 8 = 2).

calculated

EBITDA of AED 75 million on revenue of AED 287 million is a margin of 26.1% (75 / 287).

calculated

EBITDA of AED80 million on revenue of AED269 million is a margin of about 29.7% (80 / 269).

calculated

Cement division revenue rose from AED269 million in the first quarter to AED 287 million in the second, a difference of AED 18 million, while EBITDA fell from AED80 million to AED 75 million, a difference of AED 5 million.

inferred

A 30% rise in average selling prices and a 28% rise in volumes would ordinarily imply revenue growth well above the 29% reported; the price figure covers cement products while the volume figure covers cement and clinker, so the two may not be like for like.

inferred

Materials at around 60 percent of baseline costs is a 2025 figure covering all materials; it gives no weight for cement, concrete or reinforcement steel, so it does not show whether their rises since January break a forecast of around three per cent cost escalation.

inferred

Shorter price guarantees, price holds of around 30 days and greater use of fluctuation clauses move the risk of rising prices from the party quoting a price to the party paying for the building.

inferred

Higher cement selling prices are reaching a producer's accounts: reports on EMSTEEL's results tie its wider margin and higher profit to higher prices and strong demand.

testable

If EMSTEEL's cement division reports a third-quarter EBITDA margin at or above 26.1 per cent with selling prices above a year earlier, the price rises are sticking; a margin below 22.8 per cent or selling prices no higher than a year earlier would point the other way.

Alpha's read · open

Cement price rises in the UAE appear to be reaching a producer's margin while price guarantees shorten, so the buyer of construction work carries cost risk that a forecast of around three per cent escalation does not show.

Screen for this structure

Construction materials · middle-east-africa

Open in screener

Share this story